|
IT’s a verdict that may come as a
surprise to the critics who dismissed
Ramsey Pier as a rusting wreck deemed
too derelict to be worth saving.
‘In my opinion, with 40 years’
experience working on piers, this is one
of the best there is – it’s one of the
best examples of Victorian pier
engineering there is, without a doubt,’
said Mike Hawkins, managing director of
Maryport-based marine engineers MPM Ltd.
MPM contractors began work on the
stabilisation scheme in May, shortly
after Tynwald narrowly voted through the
funding approval with the closest of
margins.
The row over whether the £1.758
million could have been better spent on
other government priorities in the wake
of the VAT bombshell has continued ever
since.
There has also been criticism that
the project didn’t go to a Manx firm.
But Mr Hawkins insists that more than
half – four out of the seven – of those
working on the contract are Manx
workers.
He said the project was on schedule.
‘Progress has been good. There’s been a
few hiccups but the weather has been
reasonable and we are on schedule and
should be finished by the beginning of
November.’
Initial work involved the careful
removal of the cast iron balustrades,
lampposts, seating and other metal work
of historic value which have been
catalogued and placed into secure
storage in Jurby so they can be returned
to the pier if funding for a full
refurbishment ever becomes available in
the future.
The seaward kiosk remains for the
time being, but will be taken down in
consultation with Manx National
Heritage.
However, the main entrance is to be
refurbished to provide security while
the pier remains closed. Local
contractors will be involved in this
work.
Below deck, all the corroded steel
cross-braces are being replaced – and
all the underwater work has been
completed.
Mr Hawkins explained that while the
pier’s original cast iron piles were in
very good condition, many of the
diagonal steel struts had corroded. Some
513 have had to be replaced – about
three quarters of the total. All of the
replacement steelwork is pre-painted
before it is fitted.
Government divers helped with the
underwater work. ‘They’ve been very good
– the best set of divers we’ve worked
with,’ said the MPM boss.
Surprisingly, even the timberwork on
the deck has fared better than would be
expected, with some 50 per cent of the
hardwood decking still in reasonable
condition – again testimony to the
quality of materials used in the pier’s
construction.
Even many of the galvanised nails
were found to be nearly as good as new.
‘Compared with some of the piers
we’ve worked on, the final build was
very good which is why it is still in
reasonably good condition. The pier was
made out of very good materials, there
was no compromise in the way it was
built.’
Mr Hawkins, whose company has been
involved in a host of heritage
restoration schemes including the Houses
of Parliament and a series of Victorian
piers from Eastbourne to Blackpool and
Llandudno, said he was ‘very proud’ to
have been involved in the Queen’s Pier
project.
‘I would love to see it open. It’s an
integral part of Manx heritage,’ he
said, adding that it went without saying
that MPM would be delighted to secure
the contract for the full restoration of
the landmark, if government funding was
ever found in the future.
Full restoration of Queen’s Pier has
been priced at £9.15 million or £11.675
million if phased over a number of
years.
Mr Hawkins said that once the
stabilisation scheme was complete, it
would be ‘much more straightforward’
work to complete the pier’s restoration.
But he added: ‘It would still be
quite a specialist operation but the
awkward underwater work will have been
done. We’ve done that difficult work
labour-wise, but there would still be a
tremendous lot of construction work to
do, including the lattice girders and
the decking itself.’
FACTFILE
- 1886: Queen’s Pier built by Head
Wrightson of Stockton-on-Tees at a
cost of £45,000. At 2,150 feet in
length, it is the sixth longest pier
in the British Isles and is as long
as Snaefell is high.
- 1889: A landing stage is added
at the seaward end. The last steamer
called at the pier head in 1970.
- 1981: The pier tram stops
running
- 1991: The pier closes to the
public.
- 1995: The pier is listed as a
registered building
- 2008: A survey of 3,200
households finds that 82 per cent
are in favour of the pier being
restored.
- January 2009: Tynwald approves a
CoMin report recommending the pier
is refurbished
- May 2010: Tynwald votes to
approve a ‘de minimus’ scheme to
stabilise the pier but keep it
closed, pending future restoration.
- April 2011. Tynwald votes to
approve £1.758m for a stabilisation
scheme, by 11-10 in the House of
Keys and 7-1 in the Legislative
Council.
© Isle of Man
Newspapers. Written by Adrian Darbyshire
and published on 13th September, 2011
|